Belarus NPP construction pit concreted by 36%

29,4 thousand cubic meters of concrete have already been laid, which makes 36% of the total scope, reports interfax.by.

Such figures were announced at the session of the NPP construction headquarters, which took place in Astravets last week. It was also noted that the construction of the first level of fence around the NPP industrial field had started in the area. They plan to finish it by the end of 2012.

The protesters against the Belarusian NPP turned attention that it was being constructed with no approved project back in October.